Port Infrastructure Facilities



The reconstruction of coastal structures of the Vanino–Kholmsk automobile and railway ferry service in the seaport of Vanino is organized to restore the operational characteristics of the ferry complex. According to the project, it is planned to reconstruct the frameworks of the linkspan bridges located at berths No. 14 and No. 14a. It will allow receiving CNF11CPD-LMPP-110/5 type vessels with a length of 131 m, a width of 20.32 m, a loaded draft of 6.6 m, an estimated capacity of 30 wagons or 71 motor vehicles, and with a passenger capacity of 150 people. The implementation of the project will significantly improve passenger and transport ferry service between Sakhalin and the mainland, given the social and economic importance of the Vanino–Kholmsk ferry service for the island.

The reconstruction of coastal structures of the Vanino–Kholmsk automobile and railway ferry service in the seaport of Vanino involves:

1st stage:
- reconstruction of berth No. 14 of the ferry pier by using new technological solutions which involve formation of soil-cement mixtures in the berth body using jet cementation technology, and replacement of the inter-anchored bulwark structure of the ferry pier berth with a gravity one;
- installation of a new head for berth No. 14;
- installation of new mooring and fender facilities at berth No. 14;
- replacement of 2 linkspan bridges with railway tracks to berth No. 14;
- reconstruction of the coastal, intermediate and sea abutments of berth No. 14 by using new technological solutions which involve formation of soil-cement mixtures in the body of the abutments using jet cementation technology, and replacement of the inter-anchored bulwark structure of the abutments with a gravity one;
- major repairs of the entrance ramp to the ferry pier between the abutments;
- major repairs of the building of the ferry crossing control center;
- replacement of external and internal utility networks;
- demolition of the passenger pavilion;
- demolition of the depth-gauge building and its replacement with a modular structure.

2nd stage:
- reconstruction of berth No. 14a of the ferry pier by using new technological solutions which involve formation of soil-cement mixtures in the berth body using jet cementation technology, and replacement of the inter-anchored bulwark structure of the ferry pier berth with a gravity one;
- installation of a new head for berth No. 14a;
- installation of new mooring and fender facilities at berth No. 14a;
- replacement of the linkspan bridge with railway tracks to berth No. 14a;
- reconstruction of the coastal and sea abutments of berth No. 14a by using new technological solutions which involve formation of soil-cement mixtures in the body of the abutments using jet cementation technology, and replacement of the inter-anchored bulwark structure of the berth of the ferry pier with a gravity one;
- replacement of external and internal utility networks

Aquatic, JSC
Contract No. 91/24/1854 dated March 15, 2024
The reconstruction is to be completed on April 15, 2025.
The facility is planned to be commissioned in the 2nd quarter of 2025